Loading

CAB Min (09) 13/7: 2009 Budget Package

Cabinet Minute CAB Min (09) 13/7: 2009 Budget Package - 20 April 2009 - Budget 2009 Information Release - The Treasury
2008/09 2009/10 2010/11 2011/12 2012/13  Total 
Total 
Between Budget Spending 
Contingency 
 
 
182 
 
182 
 
182 
 
111 
 
657 
 
160 
 
10 
agreed that Ministers: 
10.1 
should only seek funding from the general between-Budget contingency for urgent 
issues that cannot be deferred to Budget 2010; 
10.2 
will be expected to demonstrate that they have considered opportunities to fund 
pressures from existing baselines before seeking funding from the contingency; 
11 
agreed that no papers with fiscal and/or appropriation implications should be submitted for 
agreement by Cabinet between now and 28 May 2009, to ensure that Budget Day 
documentation is accurate; 
 
 
CAB Min (09) 13/7 
142391v1
  
noted the impacts of the 2009 Budget Package as set out in the table below (including the 
impact of Cabinet decisions already taken): 
$million increase/(decrease) 
 
Operating Capital 
 
2008/09 2009/10 2010/11 2011/12 2012/13 
Total 
Total 
New 
spending 
223  1,801 1,427 1,808 1,839 7,099 1,392 
Savings 
(173) (272) (486) (562) (544) (2,036) (90) 
Net increase in spending 
51 
1,528 941 1,246 1,295 5,063 1,301 
 
Allowance 
1,450 1,450 1,450 1,450 5,800 1,450 
Possible 
contingency 
(51) (78) 509 204 155 737 149 
 
agreed to the initiatives for Budget 2009 as set out in the financial recommendations in the 
accompanying submission under CAB (09) 176, subject to any changes and additional 
initiatives agreed to by Cabinet in relation to specific Votes [CAB Min (09) 13/8(1-62)];  
authorised the Prime Minister and the Minister of Finance to approve changes to other 
initiatives where this proves necessary in finalising the 2009 Budget package; 
noted that the Minister of Finance intends to set aside a reasonable between-Budget 
contingency to enable the government to respond rapidly to events as they unfold: 
$million increase/(decrease) 
 
Operating Capital 
 
B09-cabmin09-13-7-1